Builder Name:William Lawrence   -  
Project:   Sonex   -   VIEW REPORTS
Total Hours:1884.3
Total Flight Time:
Start/Last Date:Nov 21, 2018 - No Finish Date
Engine:Aerovee
 
Friendly URL: https://eaabuilderslog.org?s=wlawrence

Home or Last Project Picture

Apr 03, 2021     Take Measurements Of Spar Thicknesses and Spar Tunnel Opening - (4 hours)       Category: Wings
Lee Teicheira and Bill Lawrence measured the thicknesses of the spars at the points where the bolts pass through the spar tunnel and the spars as well as the width of the tunnel and found that the thickness of the spars is too great to pass through the tunnel. Now determining the amount of the discrepancy and the best solution to remedy the problem.


 